Timeline: Vegas Raiders Stadium Would Be Finished by June 2020

LAS VEGAS (AP) — A preliminary timeline for the proposed stadium that would be home to the Raiders in Las Vegas shows construction would be finished only three months before the 2020 regular season begins.

The draft of the timeline made public Monday by the Las Vegas Stadium Authority shows construction on the proposed 65,000-seat stadium would begin in January and last 30 months, giving the team three months to move in.

Members of the board overseeing the $1.9 billion project are expected to discuss the preliminary timeline during their regularly scheduled meeting Thursday. The Raiders did not immediately respond to a request for comment from The Associated Press.

The NFL’s newest stadium took two-and-a-half years to complete. The first Minnesota Vikings preseason game at the venue took place in August.

Comments

One Comment

  1. I realize this is a large construction project requiring infrastructure for venders, suites, offices, lorckerrooms, parking and more, but’ 30 months still seems like a long time to complete.

  2. I dont want the Raiders, Oak gangs, LA gangs and Vegas gangs are all going to try and claim Vegas as their turf. Nothing but violence. Visiting teams fans wont be going to the games, they already dont go to games in Oak, so what makes anyone think they will go to them here?

Leave a Reply

Please log in using one of these methods to post your comment:

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

More From CBS Las Vegas

Introducing Your New Podcast Network Play.it
New CBS Local Sports

Listen Live